2011 |
|

|
Ship unloader and loader is delivered to the site. |
|

|
Erection of stacker-cum-reclaimer is under progress. |
2010 |
 |
Gujarat Maritme Board (GMB) grants approval for construction of the proposed port facility. |
 |
GMB grants approval for dredging the channel. |
 |
Gujarat Pollution Control Board grants consent to establish port facility. |
 |
Marine construction work and stockyard civil work commences. |
2009 |
|

|
Achieves financial closure. |
|

|
Ministry of Enevironment and Forests and Coastal Regulation Zone clearances are obtained for setting up marine facilities at Salaya. |